PRASA struggles to deploy more than half of its new trains amid signalling issues
Group CEO Hishaam Emeran has told Parliament's Standing Committee on Public Accounts that the agency has about 350 new train sets but only needs 170 to meet its current operating requirements.

A PRASA depot. Picture: @PRASA_Group/X
The Passenger Rail Agency of South Africa (PRASA) says it's struggling to put more than half of its new trains into service, with signalling problems limiting the number of trains that can operate on its rail network.
Group CEO Hishaam Emeran has told Parliament's Standing Committee on Public Accounts that the agency has about 350 new train sets but only needs 170 to meet its current operating requirements.
Emeran says the problem is a lack of alignment between the rollout of new trains and the rebuilding of rail infrastructure.
He says signalling systems are critical to increasing train frequencies, allowing services to run every 5 to 10 minutes during peak periods.
"There has been some interim work by our internal teams where they've managed to recover some of the older signalling systems, which allow us to at least run at a better frequency. You'll see some of the corridors across the country where we do have some signalling capability, but this is what we would like to see improve and ensure the full network is fully signalised."