DWS cites political instability as major contributor to delays in completing water projects
With almost all of its six mega projects reporting slow progress, director general Sean Phillips has told Parliament the political backtracking on decisions to invest in major water infrastructure, such as the Clanwilliam Dam, have contributed to the setbacks.

The Department of Water and Sanitation’s director-general, Sean Phillips. Picture: Facebook/WaterAndSanitationRSA
The Department of Water and Sanitation has cited political indecisiveness and instability over the last decade as a major contributor to delays in getting major water projects off the ground.
With almost all of its six mega projects reporting slow progress, director general Sean Phillips has told Parliament the political backtracking on decisions to invest in major water infrastructure, such as the Clanwilliam Dam, have contributed to the setbacks.
ALSO READ: Mahlobo: Criminality biggest obstacle to timely completion of water projects
The department has had five ministers since 2014, and at least eight directors general.
As members of Parliament (MPs) questioned the delays in completing the country’s major water projects, committee chairperson Leon Basson reminded the house that the department was declared technically bankrupt in 2017 during the tenure of former minister Nomvula Mokonyane.
He said it was only after former minister Senzo Mchunu took charge in 2021 that stability returned to the department and the Clanwilliam Dam project was restarted.
Phillips said political decision-making on the country’s major water projects had affected their progress.
“When new people were appointed, they rescinded decisions made by people before them and that resulted in delays.”
Phillips added that poor performance by contractors is also a major contributing factor to projects running behind schedule.
The Lesotho Highlands Project, which has also encountered political challenges, is standing at 57% complete.
Meanwhile, the Clanwilliam Dam has also made slow progress at only 47% complete.
“The procurement regulatory framework doesn’t allow you to use quality as one of the criteria for choosing contractors.”
Ten years since its start date, and with an expected December completion date, the Tzaneen Dam is around 66% complete.