Cape Town data-centre boom brings investment opportunities, infrastructure concerns
Cape Town wants to attract data centres and the investment they bring, but economist John Loos says power, water and land constraints cannot be ignored.

A water tap. Cape Town’s data-centre boom is raising questions about the city’s water, electricity and land capacity as demand for digital infrastructure grows. (Picture credit: mistac/123rf)
Cape Town's growing data-centre industry could bring investment and support economic growth, but the city's electricity, water and land constraints will have to be carefully considered, economist John Loos says.
The discussion comes as Cape Town reconsiders how it approves large data-centre developments following an appeal against a proposed Equinix project.
Data centres are increasingly important to sectors including financial services, technology, cloud computing, software and retail, while the growth of artificial intelligence (AI) is expected to add further demand.
But they are also highly intensive users of infrastructure, raising questions about whether Cape Town has enough electricity and water capacity to accommodate the sector alongside existing industries and a growing population.
Related articles:
— South Africa tipped for AI data centre boom as billions flow into new projects
— Housing Assembly raises concerns over Cape Town data centres' water, power usage
— Giant data centres get the first green light from Cape Town tribunal
— Cape Town’s data centre boom raises water and electricity concerns
— Cape Town data centre expansion could consume 34% of city’s electricity
Power demand a key concern
Loos said data centres' substantial electricity requirements should also prompt a broader discussion about South Africa's long-term investment in electricity supply.
"These data centres are energy intensive. They guzzle electricity," he said.
But Loos argued that the emergence of data centres should not be viewed in isolation from the country's existing electricity constraints.
He pointed to what he described as decades of underinvestment in electricity supply capacity, saying electricity production had declined since around 2010 while the economy had continued to develop.
In the short term, he said, available electricity supply would have to be taken into account when considering new developments.
"If you don't have enough supply, you don't have enough supply until you've created more supply," Loos said.
At the same time, he argued that the growth of data centres was part of a longer-term economic shift and that South Africa would need to expand electricity capacity to accommodate a modern, increasingly digital economy.
The interview cited claims that four major proposed facilities could require 34% of Cape Town's current electricity capacity, while the proposed Equinix facility was said to require between 160MW and 174MW.
Water and land add to the pressure
Electricity is not the only infrastructure concern.
The interview also highlighted water consumption, with civil society groups calculating that standard evaporative cooling at a 160MW facility could consume between 2 billion and 4.4 billion litres of water annually.
Loos said electricity and water supply capacity would both require long-term planning.
"Investment in water supply capacity is crucial," he said.
He acknowledged the need to balance infrastructure demands with economic growth, job creation, existing industries and households, particularly as Cape Town's population grows.
Land is another constraint.
The interview considered whether large areas of strategically located industrial land should be used for relatively low-density data-centre developments when the same land could potentially serve manufacturing or logistics.
Loos said the issue ultimately came back to infrastructure and urban planning.
Cape Town, he said, faces particularly acute land scarcity because of its geography, higher-value farmland around the city's edges and rapid population growth.
"These things become very important," Loos said, describing an increasingly significant clash between land and infrastructure demands and the needs of housing and other economic activities.
The economic case for data centres
Despite those constraints, Loos said data centres could generate significant economic benefits beyond the jobs created directly during their construction and operation.
He pointed to their role in supporting industries that already depend heavily on digital infrastructure.
"Financial services use them in a big way. Technology, cloud, software, digital services, retail uses them," he said.
Loos argued that the economic value of data centres comes largely from the efficiencies they enable across the wider economy, rather than from the number of people directly employed inside a facility.
He said these efficiencies had contributed to economic growth and job creation globally.
He also identified another potential benefit for Cape Town: attracting further investment by demonstrating that the city can accommodate businesses with significant infrastructure requirements.
Loos said Cape Town had built a reputation for providing a relatively business-friendly environment and argued that accommodating data centres could reinforce that reputation.
"If you can accommodate data centres, if it's at all possible, and you're sending a signal that you can cater for the electricity supply demands, the water supply demands, if you can, I'm saying, it continues to build that brand that City of Cape Town has already sort of established to a significant degree," he said.
AI is adding to an existing data-centre boom
Loos said the growth of data centres should not be attributed solely to the artificial intelligence boom.
He pointed to the long-term expansion of digital banking, online retail and other digital services, as well as growing use of data centres in healthcare and life sciences.
"The growth in data centres has already been rapid for a very long time," he said.
AI, however, is adding another source of demand.
Loos also linked the growing focus on keeping data within countries or regions to a broader shift in globalisation.
He said events since the COVID-19 pandemic, as well as growing geopolitical tensions, had encouraged countries and businesses to become more self-sufficient and less dependent on other countries for essential services.
For Cape Town, the challenge is therefore not simply whether the city wants data centres, but whether it can provide the electricity, water and other infrastructure needed to support them without crowding out existing demands.
Loos said the longer-term answer would require increased supply capacity for both water and electricity, alongside planning for the city's continued economic and population growth.
The economic benefits, he suggested, could extend well beyond the data centres themselves and into the wider industries that increasingly depend on digital infrastructure.