Lindsay Dentlinger14 August 2026 | 11:43

DBSA pushes back against criticism over R4.6bn Parliament rebuild price tag

It says an incorrect perception may have been created because the National Treasury had initially made R2 billion available for the project, but this was before the detailed designs and the full costs were considered. 

DBSA pushes back against criticism over R4.6bn Parliament rebuild price tag

Parliament's National Assembly under reconstruction after 2022 fire.

The Development Bank of Southern Africa (DBSA) said there has been no ballooning of costs on the R4.6 billion rebuilding of Parliament.

It said an incorrect perception may have been created because the National Treasury had initially made R2 billion available for the project, but this was before the detailed designs and the full costs were considered.

ALSO READ: Parliament rebuild: Didiza rejects DA claims of unlawful R4.6bn process

Parliament’s two main assembly buildings were gutted in an arson attack in early 2022.

On Friday, Members of Parliament peppered the DBSA and Parliament’s administration with questions about the financial management of the project, with the EFF saying nothing will ever justify spending R4.6 billion on new buildings.

The DBSA said the rebuild price tag must be viewed in terms of its individual components, with the National Assembly building to cost R2.2bn, and the restoration of the Old Assembly R1.8 bn.
Other costs include the demolition work, the building of offices for MPs and the information technology that will be required in the new buildings.

Two different contractors are working on each of the two buildings.

DBSA’s Group Executive for Infrastructure, Chuene Ramphele, said that there are misconceptions in the public domain about the expenditure.

“There are no cost overruns. We have submitted those reports to the Minister of Finance to showcase that there’s no particular overspending that has happened.”, said Ramphele.

While the MK Party’s Des van Rooyen has demanded a full breakdown of costs, including the awards of tenders and contracts to sub-contractors, the EFF’s Omphile Maotwe said the costs on this project can never be justified.

“We are not building a road here. This is not a 10km road or more. This is the building of Parliament that got burnt. And a section of it, it’s not even from scratch. So, nothing will justify it. It doesn’t matter what we say or do.”

ALSO READ: DA questions legality of Parliament rebuilding processes following 2022 fire

Secretary to Parliament Xolile George said the project is being audited by the Auditor-General and that, to date, no concerns have been raised about the expenditure.

George said he was surprised by suggestions that the rebuilding of Parliament had not followed legal prescripts.

It follows questions raised by the Democratic Alliance (DA) after Public Works and Infrastructure Minister Dean Macpherson said there appeared to be no paper trail of the department handing the project to Parliament.

MPs probed the expenditure of the R4.6 billion project, with the DA once again pressing for explanations on the legality of Parliament managing the project.

As the DA’s Rikus Badenhorst pressed Parliament’s administration to explain its takeover of the rebuild project, the African National Congress’s (ANC) Cameron Dugmore criticised Badenhorst for casting aspersions on the lawfulness of the arrangement.

George said since the rebuilding project began in late 2022, the steering committee comprising the Development Bank of Southern Africa as the implementing agency, the Department of Public Works and Infrastructure, and the National Treasury had met 11 times.

He said this matter was never at issue.

"It’s quite surprising to us. We have adequate records that demonstrate engagements between Parliament and Public Works. So, we might not know what happens on their side, in their own administration," George said.

George said the rebuilding of Parliament was being conflated with custodial issues related to the parliamentary precinct.

"At the technical level, we have standing engagements with Public Works and National Treasury on this project," he added.

National Assembly Speaker Thoko Didiza reiterated that she would call a meeting of former ministers to explain the process followed in handing the project to Parliament to manage.

Never miss a major story. Get breaking news and the latest developments from South Africa and beyond as they happen.